Overview
Best practice is only useful when it survives contact with a real programme. These are the habits we find most reliable across ERP and enterprise IT delivery.
They are deliberately unglamorous. Most of them are about making the current state visible early enough to act.
Practice 01
Make the plan reflect reality
A plan built from optimistic durations and unnamed dependencies is a communication document, not a control. We build plans from the critical path outward, with named owners, explicit assumptions, and contingency that is visible rather than buried.
Progress is reported against deliverables and decisions, not percentage-complete sentiment.
- Work breakdown to a level that can be owned
- Named dependencies across teams and vendors
- Visible contingency and assumptions
Practice 02
Manage risks as decisions waiting to happen
A RAID log is only valuable when each risk has an owner, a trigger, and a response that has been discussed. We keep the active list short and review it where decisions are made.
Issues are separated from risks so the team can act on today’s problems without losing sight of tomorrow’s.
Practice 03
Design governance for the decision
Meeting cadence, membership, and inputs should follow the decisions required at each level. Operational stand-ups handle delivery; design authorities handle fit; steering handles scope, risk, and investment.
We keep status reporting consistent so meetings are spent on judgement, not on reconstructing what happened.
Practice 04
Test and cut over with the business
Testing is not an IT phase. Business process owners should define acceptance criteria and participate in end-to-end cycles.
Cutover readiness is evidenced by rehearsals, verified data, trained users, and agreed support. The go/no-go decision should be able to point to each.
Practice 05
Plan for the first close, not just go-live
Success is often determined after the system is live. The first financial close, first payroll, and first peak period deserve their own plan.
Hypercare should have explicit exit criteria and a named permanent owner before it begins.
From the field
Illustrative example
A steering committee spends most of its monthly meeting reviewing a long status pack and leaves without resolving two scope questions. Restructuring the agenda around decisions required, risks that changed, and dependencies needing escalation gives senior leaders the information they need to decide — and returns the meeting to its proper purpose.
Continue exploring
Related capabilities
01 Lessons Learned from Various Local & Global Rollouts
Patterns that repeat across local and global rollouts — and the early decisions that change the outcome.
Explore service
03 Sample Project Plans
Reference plan structures for ERP assessments, implementation rollouts, and support transitions — ready to adapt.
Explore service
04 IT Project Manager Toolkit
The working documents we reach for most often: charters, RAID logs, status formats, decision records, and readiness checklists.
Explore service