A practical RAID log for ERP programmes
Most RAID logs become archives. A working log is short, owned, and tied to decisions — here is a structure that stays useful under pressure.
Sunny Kaul
Principal Advisor, Kaul Advisors
A RAID log is one of the first artefacts a programme creates and one of the first to stop being read. It grows into a long list of items with vague owners and no decisions, maintained because the methodology requires it.
A working log is different. It is short, it changes, and it is reviewed where decisions are made.
Separate the four categories, then connect them
Risks, assumptions, issues, and dependencies are different things. Mixing them into one undifferentiated list makes it hard to see what needs action now.
- Risks are uncertain events that could affect the programme.
- Assumptions are things believed to be true but not yet verified.
- Issues are problems that have already happened.
- Dependencies are work or decisions the programme needs from somewhere else.
The value comes from connecting them. An assumption that proves false becomes an issue. An issue may create a new risk. A dependency may be the trigger for both.
Give every item a trigger and a response
“Risk: data quality” is not actionable. It does not tell anyone when to act or what action to take.
A useful entry contains:
| Field | What it should answer |
|---|---|
| Description | What could happen, specifically? |
| Owner | Who is accountable for managing it? |
| Trigger | What signal tells us it is happening? |
| Response | What will we do if it does? |
| Date | When will this be reviewed again? |
The trigger is the field most often missing and most valuable. It turns a passive list into an early-warning system.
Keep the active list short
A RAID log with two hundred open items is not a control. It is a sign that the programme has stopped making choices about what matters.
We keep a working list of the items that could change a decision in the next reporting period. Everything else lives in a reference register. Items move onto the active list when their likelihood, impact, or timing changes.
This sounds like extra administration. In practice it reduces it, because the governance conversation focuses on a manageable set of live questions.
A RAID log should help a programme decide what to do next. If it only records what might go wrong, it is a diary, not a control.
Record decisions separately
Risks and issues generate decisions, but the decision itself needs its own record. A decision log should capture:
- the decision made
- the date and decision owner
- the options considered
- the rationale
- what changes as a result
This is particularly important in ERP programmes, where the same design question can return in a different workstream three months later. Without a decision record, the organisation relitigates it from memory.
Review in the right room
The full RAID log does not belong in every meeting. Different items need different audiences.
- Delivery stand-up: active issues and near-term dependencies.
- Design authority: assumptions and risks that affect process or solution decisions.
- Steering committee: risks and decisions that require senior authority or investment choices.
A short, consistent review at each level keeps the log current without turning governance into a reading exercise.
A simple test of health
At the end of each review, ask three questions:
- Did we close, change, or escalate at least one item?
- Does every active item have a named owner and a next date?
- Is there anything on the list that no one discussed?
If the answer to the third question is yes, the log is drifting. If the first two answers are consistently yes, it is doing its job.
Keep reading
Related articles
Toolkit The one-page program status executives actually read
A status report is a decision aid, not a diary. A simple one-page structure that respects senior attention and surfaces what needs to change.
Read article
KA Labs Designing a cutover runbook that teams actually use
A cutover runbook is not a record of intent. It is the decision tool a tired team relies on at 3 a.m. Here is how to write one that holds up.
Read article